Project Plan

PHASE ONE
Repairs and upgrades needed prior to renovation

  1. Remove existing chimneys and repair metal roof
  2. Paint metal roof, remove shingles, and repair damages wood
  3. Install three dimensional 30-year shingle with 6 feet ice shield on the remaining roof
  4. Upgrade and install HVAC system in attic with duel fuel heat pump with gas back up; make necessary repairs for proper access
  5. Install acoustical ceiling  in sanctuary with trim
  6. Install all new lighting in sanctuary

PHASE TWO
Improve handicap and egress access to the main body of the church and make church ADA compliant

  1. Demo basement and lower level bathrooms
  2. Demo kitchen and old furnace room
  3. Demo front steps
  4. Construct new front entrance
  5. Construct new addition with elevator shaft
  6. Install two-stop elevator
  7. Remodel fellowship hall with kitchen area

PHASE THREE
Interior remodeling and connecting educational building to main body of the church

  1. Demo pulpit area , pastor’s study, choir loft, and rear offices
  2. Remodel pulpit, choir loft, and pastor’s study
  3. Install new carpet and reupholster seating
  4. Install and replace selected doors and trim
  5. Painting